ArithmeticA and B can do a piece of work in 10 days and 6 days respectively. A started the work alone and then after 2 days B joined him till the completion of the work. How long did the work last ? 

A and B can do a piece of work in 10 days and 6 days respectively. A started the work alone and then after 2 days B joined him till the completion of the work. How long did the work last ? 

  1. A

    1 day

  2. B

    2 days

  3. C

    5 days

  4. D

    3 days

    Fill Out the Form for Expert Academic Guidance!l



    +91



    Live ClassesBooksTest SeriesSelf Learning



    Verify OTP Code (required)

    I agree to the terms and conditions and privacy policy.

    Solution:

    A can do a piece of  work in 1 day =110

    B can do a piece of  work in 1 day =16

    A's 2 days work =110×2=15  work

    Remaining work=115=45  work

    A and B's 1 day work = 110+16=3+530=830=415

    A & B can complete the total work in 154 days

    45th work can complete in 45×154=3 days

    So the work will complete in 3+2 = 5 days.