ArithmeticIf A and B together can complete a work in 12 days, A and C together in 15 days and B and C together in 18 days, then how long they can do the complete work

If A and B together can complete a work in 12 days, A and C together in 15 days and B and C together in 18 days, then how long they can do the complete work

  1. A

    9.7 days

  2. B

    10.4 days

  3. C

    8.8 days

  4. D

    8.6 days  

    Fill Out the Form for Expert Academic Guidance!l



    +91



    Live ClassesBooksTest SeriesSelf Learning



    Verify OTP Code (required)

    I agree to the terms and conditions and privacy policy.

    Solution:

    A & B one day work = 112

    A & C one day work = 115

    B & C one day work = 118

    A, B & C's one day work = 12(112+115+118)

    =12(15+12+10180) =37360 

    A, B & C can complete the work in =36037=9.7 days

     