Solution:
A & B one day work =
A & C one day work =
B & C one day work =
A, B & C's one day work =
A, B & C can complete the work in
If A and B together can complete a work in 12 days, A and C together in 15 days and B and C together in 18 days, then how long they can do the complete work
A & B one day work =
A & C one day work =
B & C one day work =
A, B & C's one day work =
A, B & C can complete the work in