MathematicsA can do a piece of work in 24 days. If B is 60% more efficient than A. Then the number of days required by B to do the twice as large as the earlier work isChapter/Topic:  Comparing Quantities

A can do a piece of work in 24 days. If B is 60% more efficient than A. Then the number of days required by B to do the twice as large as the earlier work is


Chapter/Topic:  Comparing Quantities


  1. A
    24
  2. B
    36
  3. C
    15
  4. D
    30 

    Fill Out the Form for Expert Academic Guidance!l



    +91



    Live ClassesBooksTest SeriesSelf Learning



    Verify OTP Code (required)

    I agree to the terms and conditions and privacy policy.

    Solution:

    We have to find the number of days B will take to finish a work that is twice as big as the earlier one.
    If a person can do a work in x days, then, we can say that in 1 day that person can do 1/x.
    A's 1 day's work =124
    We will now find the number of days required by B to do the same work as A. We know that B is 60% more efficient than A. So, the amount of work done by B in one day can be calculated as follows,
    B's 1 day's work =124​​+(60% of 124)​)​= 124​ ​×160100​​=115
    B  can  do  same  work  in 15 days
    Therefore, the number of days required by B to complete the same quantity of work as A is 15 days.
    Now, we are asked to find the number of days B will take to do a work which is twice as large as the earlier one. So, we will multiply the days taken by B to finish the earlier work by 2.
    We know that the number of days required by B to finish the original work is 15 days. So, to finish a work which is 2 times the previous work
    B  can do  double work in2×15 = 30 days
    Hence, Option (4) is the correct answer.
      
    Chat on WhatsApp Call Infinity Learn

      Talk to our academic expert!



      +91


      Live ClassesBooksTest SeriesSelf Learning




      Verify OTP Code (required)

      I agree to the terms and conditions and privacy policy.