Book Online Demo
Check Your IQ
Try Test
Courses
Dropper NEET CourseDropper JEE CourseClass - 12 NEET CourseClass - 12 JEE CourseClass - 11 NEET CourseClass - 11 JEE CourseClass - 10 Foundation NEET CourseClass - 10 Foundation JEE CourseClass - 10 CBSE CourseClass - 9 Foundation NEET CourseClass - 9 Foundation JEE CourseClass -9 CBSE CourseClass - 8 CBSE CourseClass - 7 CBSE CourseClass - 6 CBSE Course
Q.
2 women and 5 men can complete a piece of work in 4 days if the same work is completed by 3 women and 6 men will take 3 days to complete and find the time taken by one man and one woman to do the same work?
see full answer
Start JEE / NEET / Foundation preparation at rupees 99/day !!
21% of IItians & 23% of AIIMS delhi doctors are from Sri Chaitanya institute !!
An Intiative by Sri Chaitanya
a
36 and 18
b
18 and 36
c
20 and 31
d
None of these
answer is A.
(Unlock A.I Detailed Solution for FREE)
Ready to Test Your Skills?
Check your Performance Today with our Free Mock Test used by Toppers!
Take Free Test
Detailed Solution
Concept- Assume that one guy will need a certain number of days to complete the entire task, and that one woman will need a different number of days to complete the same task. Create two equations using the two conditions. Find the portion of the work done by the specified number of men and women over the specified number of days, then convert that portion to one unit of work by adding the two values. Solve both equations now.
Let's imagine that one man can finish the entire project in "x" days and one woman can finish it in "y" days. So, in x days, one man completes one unit of work.
Thus, a man can complete
the amount of work in 1 day.
In a similar vein, a woman can complete
of work in 1 day.
The fact that two women and five men can finish one unit of work in four days fulfils the first criteria. As a result, two women can complete
worth of
labour in a single day instead of only one. As a result, 2 women can complete
of work in 4 days.
As one man can complete
unit of work in one day, five men can complete
amount of work in four days.
Now, we can write the equation as follows: Men's work + Women's work = 1.
The second condition, which states that the work will be completed in 3 days by 3 women and 6 men, allows us to derive another equation.
Thus, the
work will be completed in three days by three ladies. And in 3 days, 6 men will complete
of the task. So, another equation would be: Amount of labour done by males plus Amount of work done by women Equals 1.
In order to solve equations (i) and (ii) , set
and
So, we obtain
Equation (iii) can now be expressed as,
Putting the value of "u" into equation (iv) now yields
Input the value of "v" into equation (iv) to obtain
Consequently, using the equation
and
, we can obtain the values of x and y.
As a result, one male can finish the job in 36 days and one woman may finish it in 18 days.
Hence, the correct answer is option 1.
Let's imagine that one man can finish the entire project in "x" days and one woman can finish it in "y" days. So, in x days, one man completes one unit of work.
Thus, a man can complete
In a similar vein, a woman can complete
The fact that two women and five men can finish one unit of work in four days fulfils the first criteria. As a result, two women can complete
As one man can complete
Now, we can write the equation as follows: Men's work + Women's work = 1.
Thus, the
Hence, the correct answer is option 1.
Watch 3-min video & get full concept clarity