Q.


2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days. The time taken by 1 woman alone to finish the work, and also that taken by 1 man alone is:

see full answer

Start JEE / NEET / Foundation preparation at rupees 99/day !!

21% of IItians & 23% of AIIMS delhi doctors are from Sri Chaitanya institute !!
An Intiative by Sri Chaitanya

a

36 days, 18 days

b

30 days, 18 days

c

40 days, 30 days

d

26 days, 17 days  

answer is A.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

Given 2 women and 5 men can together finish work in 4 days, while 3 women and 6 men can finish it in 3 days.
Days taken by women = x
Days taken by men = y
According to the question,
4 2 x + 5 y =1  
2 x + 5 y = 1 4       -----1
Also,
3 3 x + 6 y =1    3 x + 6 y = 1 3      ----- 2
Let 1 x =w and  1 y =m  
Modified equations are,
2w+5m= 1 4       ---- 3
And,
3w+6m= 1 3  
w+2m= 1 9       ----- 4
Multiplying by 2 on both sides,
2w+4m= 2 9  
Subtracting equation 4 from 3,
(2w + 5m) – (2w + 4m) = 1 4 2 9   m= 1 4 2 9   m= 98 36 = 1 36 .  
Now from equation,
2w+4m= 2 9 2w+4 1 36 = 2 9 2w= 2 9 1 9 2w= 1 9 w= 1 18  
Now, the values of x and y are,
m= 1 x = 1 36  
x = 36
w= 1 y = 1 18  
y = 18
The time taken by 1 woman alone to finish the work is 36 days.
Time taken by 1 man alone to finish the work is 18 days.
Hence, option 1 is correct.
 