Q.

A and B can do a piece of work in 18 days. B and C in 24 days. A and C in 36 days. In what time can they do it all working together 

see full answer

Talk to JEE/NEET 2025 Toppers - Learn What Actually Works!

Real Strategies. Real People. Real Success Stories - Just 1 call away
An Intiative by Sri Chaitanya

a

18 days

b

16 days

c

20 days

d

17 days

answer is C.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

One day work (A and B) =118

One day work ( B and C) =124

One day work of (C and A) =136

2(A+B+C)'sone day work

=118+124+136=972=18

So one day work of (A+B+C)=116

So total work can be done by (A+B+C)  =16 days

Watch 3-min video & get full concept clarity

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon