Q.

A and B can separately do a work in 6 days & 18 days. They worked together for 3 days after which

B was replaced by C. If the work was finished in next 5/3 days, the number of days in which C alone could do the work is

see full answer

Your Exam Success, Personally Taken Care Of

1:1 expert mentors customize learning to your strength and weaknesses – so you score higher in school , IIT JEE and NEET entrance exams.
An Intiative by Sri Chaitanya

a

30

b

25 

c

40

d

45

answer is A.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

A can do work in  1 day =16

B can do work in  1 day =118

Together work for  3 days [16+118]×3418×3=23  work

Remaining work =13  done  byA  &C

C can complete the work in X days.

A & C's one day work = 16+1x=6+x6x

A & C can complete the total work in 6x6+xdays

A & C can complete 13rdwork in 53days

13×6x6+x=1×53 6x=30+5x x = 30

Watch 3-min video & get full concept clarity
score_test_img

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Get Expert Academic Guidance – Connect with a Counselor Today!

best study material, now at your finger tips!

  • promsvg

    live classes

  • promsvg

    progress tracking

  • promsvg

    24x7 mentored guidance

  • promsvg

    study plan analysis

download the app

gplay
mentor

Download the App

gplay
whats app icon
personalised 1:1 online tutoring