Q.

A and B can together finish a work in 30 days. They worked on it for 20 days, and then B left. The remaining work was done by A alone in 20 more days. A alone can finish the work in:

see full answer

Want to Fund your own JEE / NEET / Foundation preparation ??

Take the SCORE scholarship exam from home and compete for scholarships worth ₹1 crore!*
An Intiative by Sri Chaitanya

a

62 days

b

58 days

c

56 days

d

60 days

answer is D.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

A and B can together finish a work= 30 days.

One day work of A and B =130

20 days work of A and B =2030

Remaining work =12030=13work

13work was done by A alone = 20 days

 Whole work was done by A alone = 20x3 = 60 days