Q.

A, B and C together can finish a piece of work in 4 days A alone can do it in 12 days and B in 18 days then C alone can do it in

see full answer

Want to Fund your own JEE / NEET / Foundation preparation ??

Take the SCORE scholarship exam from home and compete for scholarships worth ₹1 crore!*
An Intiative by Sri Chaitanya

a

21 days

b

16 days

c

14 days

d

9 days

answer is D.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

A+B+C=14

A=112,B=118

C=14112118

C=93236=436=19

C can do in 9 days.