Q.

A can do a piece of work in 10 days while B can do it in 15 days.  They begin together but 2 days before the completion of the work.  A leaves off.  The total number of days for the work to completed by B in ____ days.

see full answer

Start JEE / NEET / Foundation preparation at rupees 99/day !!

21% of IItians & 23% of AIIMS delhi doctors are from Sri Chaitanya institute !!
An Intiative by Sri Chaitanya

a

11

b

7

c

9

d

5

answer is A.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

A can do work in 10 days  Work done by A in 1 day =110

B can do work in 15 days  Work done by B in 1 day =115

Work done by A and B in 1 day =110+115=3+230=530=16

Work left =26=13

Number of days to complete the work for B=13115=5 days

Watch 3-min video & get full concept clarity

tricks from toppers of Infinity Learn

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon
A can do a piece of work in 10 days while B can do it in 15 days.  They begin together but 2 days before the completion of the work.  A leaves off.  The total number of days for the work to completed by B in ____ days.