Q.

A contract on a construction job specifies a penalty for delay of completion beyond a certain date as follows:200 for the first day, 250 for the second day, 300 for the third day, etc, the penalty for each succeeding day being 50 more than for the preceding day. How much money the contractor has to pay as a penalty if he has delayed the work by 30 days?

see full answer

Your Exam Success, Personally Taken Care Of

1:1 expert mentors customize learning to your strength and weaknesses – so you score higher in school , IIT JEE and NEET entrance exams.
An Intiative by Sri Chaitanya

answer is 1.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

A day's delay in completion carries a fine of Rs. 200 and an additional Rs 50 the next day.

We know that,

 Sn = n/2 [2a + (n - 1) d] or  Sn= n/2 [a + l].

From the given information we have,

Penalty for 1st day = Rs. 200

Penalty for 2nd day = Rs. 250

Penalty for 3rd day = Rs. 300

By observation, penalties are in A.P. 

a = 200, d = 50, n = 30

Using the above information,

Sn = n/2 [2a + (n - 1)d]

S30 = 30/2 [2 × 200 + (30 - 1)50]

= 15 [400 + 1450]

= 15 × 1850

= 27750

Therefore, the contractor has to pay Rs. 27750 as a penalty.

Watch 3-min video & get full concept clarity
score_test_img

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Get Expert Academic Guidance – Connect with a Counselor Today!

best study material, now at your finger tips!

  • promsvg

    live classes

  • promsvg

    progress tracking

  • promsvg

    24x7 mentored guidance

  • promsvg

    study plan analysis

download the app

gplay
mentor

Download the App

gplay
whats app icon
personalised 1:1 online tutoring