Q.

A contract on a construction job specifies a penalty for delay of completion beyond a certain date as follows:200 for the first day, 250 for the second day, 300 for the third day, etc, the penalty for each succeeding day being 50 more than for the preceding day. How much money the contractor has to pay as a penalty if he has delayed the work by 30 days?

see full answer

Start JEE / NEET / Foundation preparation at rupees 99/day !!

21% of IItians & 23% of AIIMS delhi doctors are from Sri Chaitanya institute !!
An Intiative by Sri Chaitanya

answer is 1.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

A day's delay in completion carries a fine of Rs. 200 and an additional Rs 50 the next day.

We know that,

 Sn = n/2 [2a + (n - 1) d] or  Sn= n/2 [a + l].

From the given information we have,

Penalty for 1st day = Rs. 200

Penalty for 2nd day = Rs. 250

Penalty for 3rd day = Rs. 300

By observation, penalties are in A.P. 

a = 200, d = 50, n = 30

Using the above information,

Sn = n/2 [2a + (n - 1)d]

S30 = 30/2 [2 × 200 + (30 - 1)50]

= 15 [400 + 1450]

= 15 × 1850

= 27750

Therefore, the contractor has to pay Rs. 27750 as a penalty.