Q.

A contract on the construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹200 for the first day, ₹250 for the second day, ₹300 for the third day, etc, the penalty for each succeeding day being ₹50 more than for the preceding day. How much money the contractor has to pay the penalty if he has delayed the work by 30 days?


see full answer

Your Exam Success, Personally Taken Care Of

1:1 expert mentors customize learning to your strength and weaknesses – so you score higher in school , IIT JEE and NEET entrance exams.
An Intiative by Sri Chaitanya

a

27,750

b

29,750 

c

28,750

d

25,750

answer is B.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

It is given that, the penalty is 200 for the first day, 250 for the second day, and 300 for the third day.
So,
200, 250, 300, ….
Above is in the form of an AP.
Here,
a=200 d=250200 d=50
The number of days delay for the work is 30, so, n = 30.
The total amount paid by the contractor as the penalty is,
S n = n 2 [2a+(n1)d]
On putting given values in above we get,
S 30 = 30 2 [2(200)+(301)50]
=15[400+29(50)]
=15(1850)
=27,750
So, the contractor has to pay ₹27,750 as a penalty.
Option 2) is correct.
 
Watch 3-min video & get full concept clarity
score_test_img

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Get Expert Academic Guidance – Connect with a Counselor Today!

best study material, now at your finger tips!

  • promsvg

    live classes

  • promsvg

    progress tracking

  • promsvg

    24x7 mentored guidance

  • promsvg

    study plan analysis

download the app

gplay
mentor

Download the App

gplay
whats app icon
personalised 1:1 online tutoring
A contract on the construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹200 for the first day, ₹250 for the second day, ₹300 for the third day, etc, the penalty for each succeeding day being ₹50 more than for the preceding day. How much money the contractor has to pay the penalty if he has delayed the work by 30 days?