A contract on the construction job specifies a penalty for delay of completion beyond a certain date as follows: ₹200 for the first day, ₹250 for the second day, ₹300 for the third day, etc, the penalty for each succeeding day being ₹50 more than for the preceding day. How much money the contractor has to pay the penalty if he has delayed the work by 30 days?


see full answer

Talk to JEE/NEET 2025 Toppers - Learn What Actually Works!

Real Strategies. Real People. Real Success Stories - Just 1 call away
An Intiative by Sri Chaitanya

a

27,750

b

29,750 

c

28,750

d

25,750

answer is B.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

It is given that, the penalty is 200 for the first day, 250 for the second day, and 300 for the third day.
So,
200, 250, 300, ….
Above is in the form of an AP.
Here,
a=200 d=250200 d=50
The number of days delay for the work is 30, so, n = 30.
The total amount paid by the contractor as the penalty is,
S n = n 2 [2a+(n1)d]
On putting given values in above we get,
S 30 = 30 2 [2(200)+(301)50]
=15[400+29(50)]
=15(1850)
=27,750
So, the contractor has to pay ₹27,750 as a penalty.
Option 2) is correct.
 
Watch 3-min video & get full concept clarity

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon