Q.


A is thrice as efficient as B and B is twice as efficient as C. If A, B and C work together how long will they take to complete a job which B completes in 10 days?

see full answer

High-Paying Jobs That Even AI Can’t Replace — Through JEE/NEET

🎯 Hear from the experts why preparing for JEE/NEET today sets you up for future-proof, high-income careers tomorrow.
An Intiative by Sri Chaitanya

a

209 days 

b

119 days 

c

3 days

d

None of these 

answer is A.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

Given, time taken to B to complete work = 10 days.
As A is 3 times efficient than B. Thus, time taken to A to complete work
= 103 days.
Now b is twice efficient than C. Thus, time taken to C to complete work
= 2×10
=20 days
Now, one day work of A, B and C (working together),
=310+110+120
=6+2+120
=920
Therefore, number of days required to finish work when all three work together,
=1one day work of A+B+C
=1209
=209 days
Option 1 is correct.
 
Watch 3-min video & get full concept clarity

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon
A is thrice as efficient as B and B is twice as efficient as C. If A, B and C work together how long will they take to complete a job which B completes in 10 days?