Q.

A man and a boy can do a piece of work in 24 days. If the man works alone for the last 4 days, it is complete in 5 days. How long would the boy take to do it alone ?


see full answer

Your Exam Success, Personally Taken Care Of

1:1 expert mentors customize learning to your strength and weaknesses – so you score higher in school , IIT JEE and NEET entrance exams.
An Intiative by Sri Chaitanya

a

100 days

b

120 days

c

140 days

d

150 days 

answer is B.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

Concept- Time and work have been concerned with the amount of time it takes an individual or a group of individuals to complete a piece of work and the efficiency with which each of them completes it.
One day's work of the man and boy Question Image20 day's work of the man and boy Question ImageThe remaining Question Image of the work is done by the man alone in 5 days, i.e., the man alone can do Question Image of the work in 1 day.
Question ImageOne day's work of the boyQuestion Image.
Therefore, it would take 120 days to complete if the boy worked alone.
Hence, the correct answer is option (2).
 
Watch 3-min video & get full concept clarity
score_test_img

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Get Expert Academic Guidance – Connect with a Counselor Today!

best study material, now at your finger tips!

  • promsvg

    live classes

  • promsvg

    progress tracking

  • promsvg

    24x7 mentored guidance

  • promsvg

    study plan analysis

download the app

gplay
mentor

Download the App

gplay
whats app icon
personalised 1:1 online tutoring