Q.
A road of 5 km length will be constructed in 100 days. So 280 workers were employed. But after 80 days it was found that only km road was completed. Now how many more people were need to finish the work in the specified time?
see full answer
Want to Fund your own JEE / NEET / Foundation preparation ??
Take the SCORE scholarship exam from home and compete for scholarships worth ₹1 crore!*
An Intiative by Sri Chaitanya
a
480
b
80
c
200
d
100
answer is A.
(Unlock A.I Detailed Solution for FREE)
Ready to Test Your Skills?
Check your Performance Today with our Free Mock Test used by Toppers!
Take Free Test
Detailed Solution
280 persons worked 80 days to complete 3500 meters road.
So that a person can complete the work perday is
So to complete meters, we need man days
to complete the abvoe task in 20 days, we need to get the people
Watch 3-min video & get full concept clarity