Q.

If 12 men or 15 women or 18 boys can do a piece of work in 15 days of 8 hours each, find how many men assisted by 5 women and 6 boys will finish the same work in 16 days of 9 hours each.

see full answer

Talk to JEE/NEET 2025 Toppers - Learn What Actually Works!

Real Strategies. Real People. Real Success Stories - Just 1 call away
An Intiative by Sri Chaitanya

a

4 men

b

8 men

c

2 men

d

6 men

answer is B.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

Given, 

12 men=15 women =18 boys

1 Man = 1.5 boys, 1 woman= 6/5 boys.

Now,

SW+ 6B = 12B

Required answer is calculated as follows :

Total no. of boys reqd

=18×[(15/16)×(8/9)]

=15 boys

The number of boys already present= 12.

Hence, 3 boys more required.

But 3 boys =2 men. 

So, 2 men are required.

Watch 3-min video & get full concept clarity

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon