Q.

If  5 men or 3 boys can do a piece of work in 10 days, the number of days required to complete the work by 6 men and 2 boys is

see full answer

Start JEE / NEET / Foundation preparation at rupees 99/day !!

21% of IItians & 23% of AIIMS delhi doctors are from Sri Chaitanya institute !!
An Intiative by Sri Chaitanya

a

5514

b

8.2

c

713

d

6.4 days

answer is A.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

5  m  (or)  3  boys5m=3bm=35b(1)

b=53m

  6m+2b=x

6m+2×53m=x

6m+103m=x18m+10m=3x28m=3x

m=3x28

5m=1028m3=x

M1D1=M2D2

50=283xx=15028=7514

x=5514  days