Q.

If  5 men or 3 boys can do a piece of work in 10 days, the number of days required to complete the work by 6 men and 2 boys is

see full answer

Your Exam Success, Personally Taken Care Of

1:1 expert mentors customize learning to your strength and weaknesses – so you score higher in school , IIT JEE and NEET entrance exams.
An Intiative by Sri Chaitanya

a

5514

b

8.2

c

713

d

6.4 days

answer is A.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

5  m  (or)  3  boys5m=3bm=35b(1)

b=53m

  6m+2b=x

6m+2×53m=x

6m+103m=x18m+10m=3x28m=3x

m=3x28

5m=1028m3=x

M1D1=M2D2

50=283xx=15028=7514

x=5514  days

Watch 3-min video & get full concept clarity
score_test_img

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Get Expert Academic Guidance – Connect with a Counselor Today!

best study material, now at your finger tips!

  • promsvg

    live classes

  • promsvg

    progress tracking

  • promsvg

    24x7 mentored guidance

  • promsvg

    study plan analysis

download the app

gplay
mentor

Download the App

gplay
whats app icon
personalised 1:1 online tutoring