Q.

If 52 men can do a piece of work in 27 days, how long will 39 men take to complete the same work 

see full answer

High-Paying Jobs That Even AI Can’t Replace — Through JEE/NEET

🎯 Hear from the experts why preparing for JEE/NEET today sets you up for future-proof, high-income careers tomorrow.
An Intiative by Sri Chaitanya

a

35 days

b

36 days

c

37 days

d

40 days

answer is B.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

Question Image

 

 

 

Taking  x1=52,x2=39,y1=27,y2=y

By the problem  x1y1=x2y2

52×27=39×y2

y2=52×2739=36days

39 men will be the work in 36 days.

Watch 3-min video & get full concept clarity

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon