Q.

If A, B, C can do a work in 90, 30 and 45 days respectively. If they work together, the time taken to complete the work is

see full answer

Start JEE / NEET / Foundation preparation at rupees 99/day !!

21% of IItians & 23% of AIIMS delhi doctors are from Sri Chaitanya institute !!
An Intiative by Sri Chaitanya

a

15 days

b

10 days

c

20 days

d

25 days

answer is A.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

A=901 day work=190

B=301 day work=130

C=451 day work=145

A+B+C=190+130+145=2+6+4180=12180=115

A,B,C can finish in 15 days.