Q.

P can do(1/4 )th of work in 10 days, Q can do 40 % of work in 40 days and R can do (1/3)rd of work in 13 days. Who will complete the work first?

see full answer

High-Paying Jobs That Even AI Can’t Replace — Through JEE/NEET

🎯 Hear from the experts why preparing for JEE/NEET today sets you up for future-proof, high-income careers tomorrow.
An Intiative by Sri Chaitanya

a

Both P and R

b

R

c

Q

d

P

answer is C.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

According to question

P can do =14th part of work in10days; 

So entire work is done in 10 x 4 = 40 days.

Q can do 40 % of work in 40 days; 

So 100 % work is done in 100 days

R can do = 13rd  part of work in 13 days;

 So entire work is done in 13 x 3 = 39 days.

R will complete the work first.

Watch 3-min video & get full concept clarity

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon