Q.

Pooja and Ritu can do a piece of work in 1717days. If one day work of Pooja is three fourth of one day work of Ritu then find in how many days each alone will do the same work.


see full answer

Your Exam Success, Personally Taken Care Of

1:1 expert mentors customize learning to your strength and weaknesses – so you score higher in school , IIT JEE and NEET entrance exams.
An Intiative by Sri Chaitanya

a

Pooja in 40 days and Ritu in 30 days

b

Pooja in 60 days and Ritu in 40 days

c

Pooja in 30 days and Ritu in 10 days

d

Pooja in 45 days and Ritu in 20 days 

answer is A.

(Unlock A.I Detailed Solution for FREE)

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

Detailed Solution

Given work done by Ritu and Pooja.
Let the work done by Pooja in one day be 1x and work done by Ritu in one day be 1y .
Therefore, according to the question total work done by both in one day,
1x+ 1y =11717=7120 .....(1)
Also, one day work of Pooja is three fourth of one day work of Ritu,
1x =34×1y…………..(2)
Substituting above equation in equation (1), we get,
34× 1y+ 1y =7120
 74y =7120
y=30 days
Substituting y=30 in equation (2) we get,
1x =34×130
x=40 days
Hence Pooja will complete the work in 40 days whereas ritu in 30 days.
Therefore, option (1) is correct.
 
Watch 3-min video & get full concept clarity
score_test_img

courses

No courses found

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Get Expert Academic Guidance – Connect with a Counselor Today!

best study material, now at your finger tips!

  • promsvg

    live classes

  • promsvg

    progress tracking

  • promsvg

    24x7 mentored guidance

  • promsvg

    study plan analysis

download the app

gplay
mentor

Download the App

gplay
whats app icon
personalised 1:1 online tutoring