Q.

Shwetha takes 6 days less than the number of days by Ankitha to complete a piece of work. If both Shwetha and Ankitha together can complete the same work in 4 days. In how many days will Ankitha alone complete the work?


see full answer

Talk to JEE/NEET 2025 Toppers - Learn What Actually Works!

Real Strategies. Real People. Real Success Stories - Just 1 call away
An Intiative by Sri Chaitanya

a

7 Days

b

10 Days

c

12 Days

d

3 Days 

answer is C.

(Unlock A.I Detailed Solution for FREE)

Ready to Test Your Skills?

Check your Performance Today with our Free Mock Test used by Toppers!

Take Free Test

Detailed Solution

Le the number of days Ankitha takes to complete the work be x
It is given the shwetha takes 6 days less than the number of days taken by Ankitha to complete a piece of work, therefore, the number of days Shwetha takes to complete the work is (x-6)
Now, amount of work done by Ankitha together can complete the same work in 4 days, therefore, amount of work done by both in 1 day is Question ImageThus, we have
Question Imagex=2, can not be taken because x − 6 will become −4
Thus, x=12.
Hence, the number of days Ankitha alone takes to complete the work is 12 .
 
Watch 3-min video & get full concept clarity

Best Courses for You

JEE

JEE

NEET

NEET

Foundation JEE

Foundation JEE

Foundation NEET

Foundation NEET

CBSE

CBSE

score_test_img

Get Expert Academic Guidance – Connect with a Counselor Today!

whats app icon